Concrete inground pool installation process and timing

How long does it take to install a concrete swimming pool in the GTA?

Building a concrete inground pool is an exciting project that can transform your outdoor space into a luxurious retreat, but it’s important to understand the timeline involved. From initial planning and permits to excavation, construction, and final touches, creating a custom concrete pool is a complex process that requires careful coordination and craftsmanship. While the exact duration can vary depending on factors like design complexity, weather, and contractor schedules, most  projects will take 10 days complete the concrete pool build from the first day of excavation, and the landscaping portion could go from 2 days to 2 weeks depending on the project scope. In this blog, we’ll break down each phase of the process to give you a clear idea of what to expect and how to plan for your dream pool.

Building a Concrete Pool: The Process

Understanding the steps involved in building a concrete pool will give you a better appreciation of the value and effort required. Here’s a breakdown of the typical process after we finalize the concrete pool design, which includes the size, depth (shallow and deep ends), and any additional features like benches, steps, or ledges.

timeline_pre_loader
Site Layout and Approval

Prior to breaking ground, we pin out the pool’s location in your backyard to ensure it flows well with the overall landscape design and provides space for all desired features (e.g., swimming area, seating, lounging, BBQ area). This step typically takes 1-3 hours with the homeowner.

Excavation

Once the layout is approved, our excavation team begins the concrete pool build process. This starts with laying protective mats and removing any fence posts to prevent damage. Then, we begin digging the pool, which usually takes 3-4 days.
Plumbing and Electrical Setup
Pool Framing

Next, we frame the pool structure in preparation for the shotcrete application. This step usually takes 1-2 days.

Rebar Installation

We install 10mm rebar spaced 12 inches apart throughout the pool. This process can take 3-4 days to complete.
Concrete Application

Once the plumbing, framing, and rebar are ready, we apply 12″-16″ of 35 MPa concrete with a 75mm slump. The rough finish ensures that the marbelite/pebblerock will bond properly. This process typically takes one day.

Tile and Coping Installation
Landscaping
Marbelite Application
Pool Start-Up and Chemical Maintenance